Practice Management Member Conversations

 View Only

Community HTML

Clouds

Quick Links

Who we are

The Practice Management Knowledge Community (PMKC) identifies and develops information on the business of architecture for use by the profession to maintain and improve the quality of the professional and business environment.  The PMKC initiates programs, provides content and serves as a resource to other knowledge communities, and acts as experts on AIA Institute programs and policies that pertain to a wide variety of business practices and trends.

    

  • 1.  BIM Change Orders

    Posted 09-19-2023 12:12 PM

    My office recently received a change order on a project that had contractor BIM costs associated with it. The contractor BIM costs were more than the cost of the work in the change order. Does anyone have experience with a similar situation? How did you resolve it?



    ------------------------------
    Gregory Swanson AIA
    State of Illinois
    Springfield IL
    ------------------------------


  • 2.  RE: BIM Change Orders

    Posted 09-20-2023 06:21 PM

    I suggest reading your contract's general conditions to see what is included in the definition of "overhead" for changes. 

    If the BIM work is only for contractor's convenience, it would seem to be their cost, not to pass on to you.

    If you require that they turn over BIM documentation at closeout as a form of as-builts, there might be a leg for them to stand on.

    Then, talk to whoever is responsible for editing your general conditions and come up with something that is reasonable and fair, for future projects. 



    ------------------------------
    Joel Niemi AIA
    Joel Niemi Architect
    Snohomish, WA
    ------------------------------



  • 3.  RE: BIM Change Orders

    Posted 09-21-2023 08:36 PM
    Just a few thoughts.......

    In the General Conditions if Division 01 - Close out Document requires the contractor to document field changes in a BIM platform - a request for additional compensation should be rejected for BIM updates since they should have had the cost in their original General Conditions costs.  

    In Division 01 - Submittals, if the contractor is required after contract execution to do new or multiple shop drawing revisions in a BIM platform do to architect design changes onj a shop drawing (which is bad practice), those BIM costs may then be valid to request additional compensation.

    Michael L. Katzin, AIA

    p | 470.469.5586 

    e | mlkatzin@gmail.com 

    Member | City of Johns Creek Planning Commission






  • 4.  RE: BIM Change Orders

    Posted 09-22-2023 05:29 PM
    Just a few thoughts.......

    In the General Conditions if Division 01 - Close out Document requires the contractor to document field changes in a BIM platform - a request for additional compensation should be rejected for BIM updates since they should have had the cost in their original General Conditions costs.  

    In Division 01 - Submittals, if the contractor is required after contract execution to do new or multiple shop drawing revisions in a BIM platform do to architect design changes onj a shop drawing (which is bad practice), those BIM costs may then be valid to request additional compensation.

    Michael L. Katzin, AIA

    p | 470.469.5586 

    e | mlkatzin@gmail.com 

    Member | City of Johns Creek Planning Commission






  • 5.  RE: BIM Change Orders

    Posted 09-27-2023 08:34 AM
    Thank You Michael for the insights. I agree with your statements.

    Cordially Yours,

    Jose Mejia
    Project Associate
    GMK
    Palm Beach, FL
    475-3555247