Construction Contract Administration

 View Only

A crane

Quick Links

Who we are

The Construction Contract Administration Knowledge Community (CCA) has been established to help our members better understand the issues, actions and resultant impact of the decisions required in this often neglected part of Project Delivery. It is our goal to provide clear answers to issues of concern to the Institute’s membership and share case studies and best practices. We further hope to provide guidance and direction in developing guidelines for new and evolving approaches to Project Delivery as well as guidance in the continuing education of our emerging young professionals.

     

How to connect

- Join to get occasional emails with new content and resources.
- Post on the discussion board to ask questions and share ideas.
- Read a CCA white paper - or contribute your own!
- Attend an upcoming event such as webinars and conferences.
- Provide feedback on what you'd like to see from your CCA community at cca@aia.org.

An architect’s field reports

By Michael E. Plottel FAIA posted 12-04-2018 09:55 AM

  

An architect’s field reports

By Michael Plottel, FAIA, LEED AP

A CCA white paper, submitted November 6, 2018

 

Almost no one ever reads a field report, except when things go really wrong.

Think of field reports as the “black box recorder” of the construction process, or the unsung hero of effective construction contract administration. The architect—via the field report—tracks progress, monitors conformance to design intent, provides a record of work underway, and (when methodically kept) offers protection in disputes stemming from builder errors and omissions.

Keeping a consistent record of field activities across your entire practice is a good habit even if your contract includes minimal CA. Once you set foot on a job site, be prepared to record and publish your observations, preferably with supporting photos, on a standard form: 

On your letterhead, describe:

  1. Context: Project ID, report #, date, time onsite (arrival and departure), and weather. (Always note the weather even on interior work. Outside conditions such as high ambient humidity can affect progress of work or create issues later on).
  2. Builder’s resources: Trades on site, number of personnel for each trade, machines or tools in use, materials on site and adequacy of material storage
  3. Construction progress: work in place against the project schedule, work in place by trade, planned activities and adequacy of coordination, regulatory conformance and signoffs
  4. Look ahead: Submittals, long lead Items, open issues from past reports
  5. General conditions: housekeeping, site safety
  6. Quality: Conformance with design intent and construction documents, observations re workmanship and acceptance

You can organize your field report to support requisition signoffs: structure items #2, and #3 above to follow the schedule of values. Discrepancies between observed progress and requisition percentages can flag problems.

Write simple sentences. Get to the point, don’t embellish. Document clearly. Clarity, consistency, and simplicity enhance the report’s effectiveness.

 

Disclaimer: The viewpoints expressed in this article are those of the author(s) and are not necessarily approved by, reflective of or edited by other individuals, groups, or institutions. This article is an expression by the author(s) to generate discussion and interest in this topic.



This white paper is also available as a download at https://network.aia.org/constructioncontractadministration/viewdocument/an-architects-field-reports