Blogs

Traditional Project Delivery Method includes Additional CA Services for Better Results

By Morgan B. Jones posted 12-08-2011 08:53 AM

  
Even traditional project delivery methods have room for alternatives. Take mOrphosis, for example. Aleksander Tamm-Seitz, the project designer for the Perot Museum of Nature and Science, splits his time between the job-site in Dallas, Texas, and the office in Los Angeles, California. Most design firms would leave Construction Administration up to a local architect-of-record. Morphosis, however, operates as a full-service design firm and an architect-of-record in its own right.

The project was awarded to mOrphosis through the typical RFQ and interview process. After selection, mOrphosis engaged a local architect, at the request of the owner, as a consultant to help with the local permitting process and other pertinent issues. In the pre-design phase, mOrphosis assisted the owner in the selection of a Construction Manager. The owner and CM entered into a contract for a Guaranteed Maximum Price (GMP) with Design Assist. The CM became an integral part of the project team throughout the design process.

The project only strays from the traditional GMP with Design Assist in the Construction Administration Phase. Morphosis believes that it is in the client’s best interest if there is at least one member of the design team on-site during the construction process, preferably the whole design team. This expanded scope of services, however, must be included in the contract. Most owners see the benefit of bringing the contractor in early. With a little education, they can also see the benefit of increasing the presence of the architect on the job-site. This scope can then be added to the contract.

The project designer is the only one who knows the full extent of the design intent; the complexity of mOrphosis’ projects does not lend itself to being conveyed through drawings. The client and CM benefit from easier and faster access to the design architect when design issues arise. The designer’s presence can limit and address change orders and RFIs, as well as clarify design intent, and facilitate a smoother construction process The on-site designer has the same contractual relationship that is found in traditional contract documents. The same channels of communication exist. He is unable to direct sub-contractors; all communication must be directed through the CM. There is no inspecting or testing; he is simply there to observe and report. "We're here to help the contractor," says Tamm-Seitz of his role on the project site.

In the case of the Perot Museum, the project designer spends 2-3 weeks on-site and then returns to the L.A. office for 2-3 days for meetings with the entire design team and consultants. Similarly, the project architect spends the majority of his time in the L.A. office handling the technical side of project management, but occasionally travels to Dallas to meet with the CM. Tamm-Seitz joked that "it's feasible to fly between Dallas and L.A. every two to three weeks; it's not feasible to do the same if the project is in Shanghai".

Regardless of contract structure, all parties have the same goal: to produce a great building. Through early collaboration, the design team facilitates a greater understanding of the project by all parties. Through this project understanding, the CM knows what is expected as far as quality and design intent. "It is in the CM's best interest to solve issues in their construction sequence," says Tamm-Seitz. He shared that his CM will come to him with items he knows are unacceptable, rather than waiting to address them later. Similarly, Tamm-Seitz says that he might occasionally give the GC a heads-up on issues that may arise in an upcoming Observation Report in order to foster a good working-relationship with the GC.

Through additional services, mOrphosis is able to better serve its clients without entering into a full-blown Integrated Project Delivery method. The early collaboration, lines of communication, and shared goals are all the same as in IPD, they are just structured differently in the contract.


2 comments
228 views

Comments

06-13-2016 02:41 PM

Los Angeles Unified School District also sees the value of additional on-site Architecture representation during construction and has had us staff the construction trailer with up to 2 full time Project Architects on some of our larger projects. It is not always easy to educate Clients as to the value and often even more difficult to educate them that standard Construction Administration Services, provided in the contract, do not cover the level of service many projects require. We find that one approach to extending the number of hours is to identify the numbers of hours available during CA in the contract and discuss with the Owner and Contractor to determine if those hours meet the needs of the Project. In many cases, it will be clear that the typical 15% - 20% of the fee dedicated to the CA phase will be inadequate for the challenges of the project.

12-13-2011 02:43 PM

We are doing this exact thing, be it on a smaller scale, on every project. We are calling it "architect as owner's rep." and charge an additional fee. It benefits all parites (owner - better project; contractor - less problems; architect - additional fees).