Small Project Design

 View Only

Community HTML

BI(h)OME (by Kevin Daly Architects)

Quick Links

Who we are

AIA Small Project Design (SPD) Knowledge Community supports, celebrates, and promotes small projects by engaging designers and the public.

Small Project Design Forum at AIA24

Expand all | Collapse all

Closed cell shortage, GC obligation?

  • 1.  Closed cell shortage, GC obligation?

    Posted 12-04-2021 05:39 PM
    We designed a small residential addition and three days before the insulation was to be installed the contractor informed me that there is a shortage of closed cell nationally. He said the insulation price has doubled and that the owner had to eat that or accept an alternate insulation for the walls which would also meet code....but still see an overall price increase.
    I checked with insulators I've workded with and they confirmed a shortage and price increases. My question is, how much of the price increase should the owner bear? If I were the owner, I would not want to pay more than what is in the contract.  The job has had delays, most of which are of the contractor's doing. If the GC had let the insluation contract when he signed the agreement with the owner, this would not be an issue. And it would be less of an issue (ie less signfinicant price increase) if there had not been delays. I could understand some price increase but it is clear to me that the GC as not been in touch with his insulator until the last minute. I want to be fair to the GC and, of course, to my client. Thoughts?

    ------------------------------
    Thomas Ahleman AIA
    Principal
    Studio Talo Architecture, Inc.
    Evanston IL
    ------------------------------


  • 2.  RE: Closed cell shortage, GC obligation?

    Posted 12-06-2021 05:43 PM
    The first step would be to look at the owner/contractor agreement. Did the contractor commit to a fixed price at the start?

    Sincerely,


    Jody Keppers, AIA, LEED AP, NCARB
    Licensed Architect in Minnesota & Wisconsin

    Mailing Address:
    Keppers Design Architecture
    620 Ridgewood Road
    Duluth, MN 55804

    Downtown Office:
    301 West Superior Street
    Duluth, MN 55810

    218-409-6409
    jkeppers@keppersdesign.com
    www.keppersdesign.com




  • 3.  RE: Closed cell shortage, GC obligation?

    Posted 12-07-2021 06:06 PM
    I think in the current situation with supply chain issues everyone needs to have some flexibility in how things like this are handled.  even if the contract did not specially have a cost escalation clause, the pandemic and supply issues could not have been anticipated.  I have a project with a door on a slow boat from China, then stuck in the port at Long Beach for weeks.  No one at fault.    We ordered the door from a supplier in Indiana, we had no idea they sourced it form China, until we were told of the delivery challenges. Another  job took seven months to get custom, walkable skylights made, the glass came from Portugal, who would have known.

    We do Design and Build so I may be more sensitive to the plight of the GC here.  We added a "Covid Clause" to our contracts to receive us of liability of these supply chain issues.

    Thanks,



    Jim Zack, AIA | principal




    t.  415.495.7889, ext. 201
    c. 415.797.2282


    We moved, new Address:

    1672 15th Street
    San Francisco, CA • 94103







  • 4.  RE: Closed cell shortage, GC obligation?

    Posted 12-08-2021 03:22 AM
    Things to consider:
    #1, The Contract: is it a stipulated price?  If yes, the Contractor is bound to deliver for that price.  But see #3 and #5, below.
    #2, Try to avoid demanding to go into the weeds of what the subcontractor's original proposal quote was.  Going there sets you up for interfering with the GC's privileged information, means and methods of getting things done, and will create hard feelings.  IF the GC volunteers to share the information, certainly look at it - don't pass up that opportunity.
    #3,  If indeed "everyone" is having this happen, due to unforeseeable market conditions, this could be a "force majeure" situation where the specialist and the GC were helpless to prevent the price increase.  It will take a lot of legal costs on all sides to get to that point, and a lot of work won't happen on the job.
    #4,  Consider figuring out a half-way point on the pricing.  Materials cost more, yes, but no upcharge for labor.  Maybe just spray-foam the really critical and hard to seal places, and use other products elsewhere.  Document what you decide to do, and get everyone to sign off.
    #5,  What's the worst that could happen?  GC decides to unilaterally terminate the contract, walks off the job.  Now you have to find someone else to inspect and figure out what needs to be done, work it into their schedule .... and deal with a structure that might not have been weather-sealed for the winter.  Even if you / Owner goes after the GC's bond, don't expect much help there ($12,000 maximum out here in Washington).

    --
    best regards,
    Joel Niemi
    - Architect
    425.422.4276
    jniemiarchitect@gmail.com
    http://www.linkedin.com/in/jniemiarchitect





  • 5.  RE: Closed cell shortage, GC obligation?

    Posted 12-09-2021 07:08 PM

    There is also a legal term called betterment. Even when mistakes are made, an owner still has to pay the cost of items received.


    Sent via the Samsung Galaxy S9, an AT&T 5G Evolution capable smartphone






  • 6.  RE: Closed cell shortage, GC obligation?

    Posted 12-10-2021 07:13 PM
    You're thinking of value-added change orders, where, for instance, the item the architect forgot to include would have cost the Owner the same had it been included in the bid documents as it did when it was added later.  The Owner does not get it for free just because it was omitted from the construction contract by mistake.  Here, there is no omission, or "betterment," just a price increase that was not foreseen.  

    Sent from my iPhone
    -Doug Julien





  • 7.  RE: Closed cell shortage, GC obligation?

    Posted 12-06-2021 05:53 PM
    I would say under the current climate of shortages and supply chain issues, which are global, and everyone is aware of them, this is not on the contractor's fault, so the owner should bear the cost increase.  


    Thanks,


    Jim Zack


    We Moved!

    New address below.


    Zack/de Vito Architecture + Construction
    1672 15th Street
    San Francisco, CA  94103

    w. 415.495.7889 ext. 201
    c.  415.797.2282















  • 8.  RE: Closed cell shortage, GC obligation?

    Posted 12-06-2021 05:59 PM
    You should ask the GC for the proposal from the insulator that he got when he initially bid the project. Most subcontractors bids are good for 30 days, or some defined timeframe, and if he formally accepted the bid within the timeframe, then the subcontractor is obligated to hold his price. Unless he has any clause in the proposal regarding material cost escalations. In which you should get a copy of the signed contract or proposal. If the GC never formally signed the proposal, which many do not as they want to bid shop after award, then the contractor will could have some liability for not securing the bid earlier.  Since you have discussed this with other insulators, see if you can find out when this shortage and price increase occurred. This may inform you know if this was something recent or was awhile ago. Also look at the contract for construction between the Owner and GC to see if there is any language about material cost increases. 

    If there is little or no contract language anywhere for this, you should have the GC rebid the insulation to several subs to get the best price possible, even if it is more than the original. This would be the most equitable way to resolve the situation.

    Jeffrey Bumb AIA
    St. Louis MO





  • 9.  RE: Closed cell shortage, GC obligation?

    Posted 12-06-2021 06:10 PM
    Thomas,
    I think it comes down to the contract between the CG and client. It depends how that is worded if additional costs are warranted or not. If the owner and GC locked in a price and the owner has performed within the contract then it's on the GC and their sub to cover the additional cost. If the owner has caused delays and the GC has notified them that the delays would increase the cost then that's a different story. The drastic increase in costs and material availability is causing havoc for architects.

    ------------------------------
    Steven Kordalski AIA
    Kordalski Architects, Inc.
    Cleveland OH
    ------------------------------



  • 10.  RE: Closed cell shortage, GC obligation?

    Posted 12-07-2021 06:06 PM
    A lot of contractors have been caught with the escalating cost of materials. From what we hear there is a major supply chain issue with insulation. Commercial walk in refrigerators for restaurants are being canceled, back order or doubled in cost even with signed purchase order. The restaurant equipment manufacturers can’t find insulation and workers. You can’t provide what is not on the market.

    You need to have a meeting between the contractor and the owner. Let him make the case and explain the options. If the Owner wants to cut a deal, all’s well. If the Owner wants to fight for a fixed price, he may end up paying in other ways. I think this is one of those ethics questions.




  • 11.  RE: Closed cell shortage, GC obligation?

    Posted 12-07-2021 09:58 AM
    The fundamental question is: what is in the contract? That should illuminate the issue. Cost plus, stipulated sum, negotiated bid? Each have a different determination of GC obligations. I suggest  GC and owner include the reality of price increases over time, including possible savings (wishful thinking), in future project contracts.

    ------------------------------
    Peter Foxley
    Principal
    foxleyarchitecture
    Pearland TX
    ------------------------------



  • 12.  RE: Closed cell shortage, GC obligation?

    Posted 12-09-2021 09:26 AM

    And here is a new one that I was just informed of by a client- the termite treatment companies (widely and often used in Florida) will no longer provide a termite bond for homes with Icynene insulation (at least in the attic) because it covers some of the wood so it is no longer visible. Have others heard this? I personally have not had time to check with the local termite treatment companies in the area to confirm this is the case.

     

    Jim Stergas