March 13, 2012 11:43 AMBenjamin Albu...
 

Use of A103 Contract
From: Benjamin Albury, Intl. Assoc. AIA
To: Small Project Practitioners
Posted: March 13, 2012 11:43 AM
Subject: Use of A103 Contract
Message:
This message has been cross posted to the following Discussion Forums: Small Project Practitioners and Practice Management Member Conversations .
-------------------------------------------


-------------------------------------------
Benjamin Albury Intl. Assoc. AIA
Senior Partner
Albury Associates Limited
Nassau
When using the A103 Form of Contract(Cost of Works Plus Fee without a Guaranteed Maximum Price) there is obviously no Original Contract Sum(Line 1), when completing the G702 Document, Application and Certificate for Payment.
We have noted NA (Not Applicabe) in the dollar value column leading to the Total Completed & Stored line (Line4).
Is there another recommendation for completing this portion of the Certificate For Payment?
A response would be greatly appreciated.
Benjamin.
-------------------------------------------